Eversource will be installing approximately 1,080 linear feet of electric conduit in Menauhant Road, between Acapesket Road and Green Harbor Road, beginning today (1/17/23). See the map below depicting the work area.
Expect traffic delays in this area. Construction will be limited to Monday through Saturday, 7 AM to 3:30 PM, excluding holidays. Traffic control measures will be utilized. Full lane pavement replacement will be done once the job is complete. It is anticipated that this project will take until February 17, 2023 to complete. We thank you for your patience.
Electric Conduit Work Area Map (click me)