Contractor will be doing paving work on Friday 4-19 at the intersection of Brick Kiln Road and Ox Bow.
Traffic detour on Brick Kiln Road eastbound will continue through at least Tuesday April 23rd.
By late Tuesday and or early Wednesday we will be on Teaticket Highway going westbound.
Electronic bill boards will be out on Monday warning about upcoming traffic impacts.
During the work day from 7AM to 5PM traffic will be one lane only on Teaticket Highway.
Police details will manage the alternating traffic flow.
Go to http://www.falmouthmass.us/986/Traffic-Updates to see the latest traffic plan