We will continue to install the 16 inch water main in Teaticket Highway Monday through Thursday next week.
We will not work on Friday the 24th to minimize any traffic impacts as we roll into the Memorial Day Weekend.
As of Friday the 17th we have switched the alignment of the pipeline from the North Side of Route 28 to the South Side of Route 28.
We have a request in with Mass DOT to allow us to continue to construct after Memorial Day weekend up to Friday June 14th.
We anticipated a favorable decision on that request.
Go to http://www.falmouthmass.us/986/Traffic-Updates to see the latest traffic plan