We start up with the water main construction again tomorrow, December 31 on Main Street just passed the village green.
Until we get to Post Office Lane we will have alternating one way traffic – expect some delays.
Once we get to Post Office Lane and as we proceed over the next few weeks down main street we will be closing down the road on a block by block basis during the daytime.
We expect to install a least 150 feet each day will need 3-4 days for each block of work.
Pavement is only available one day each week, typically this will be Friday.
We will backfill and compact the trench each night but travel will be a little rough – similar to the work we did on Palmer Ave from Coffee O to the Green.
Parking will be prohibited within the block that we are working on. This is an inconvenience – however it allows us to get through each block in ½ the time it would take if cars were parking in that area.
As always, we appreciate your understanding as we create a mess and upgrade the water system downtown.
We are doing this through the winter to minimize disruption during the other three seasons.