Today we are doing a fire service on Main Street, we will start a second one both near 8 cousins book store.
We have one water service after that at 365 Main Street – Longfellow and the Tanning center.
We expect to be done with service work on Main Street up to Nye Road by Wednesday, Thursday at the latest.
Pipe install crew will then be moving back to Teaticket Highway to complete 4 services between Sandwich Road and Jones Road.
That will run into next week to complete.
We begin a push on paving this week and through the end of the month. Current schedule is:
Here’s how the rest of the month looks as far as milling and paving for the water main project:
Tuesday 6/9 thru Thursday 6/11
Mill and Overlay
North Main Street between Palmer Ave. and West Main Street
Mill and Overlay West Main Street
Mill to town hall square if time allows
Monday 6/15 and Tuesday 6/16
Mill and Overlay
Complete mill and overlay through downtown to Shore Rd.
Monday 6/22 thru Friday 6/26
Full Depth Pavement Patch
Jones Road to School Admin. Building