Water main construction will continue through the end of January and into early February.
The week of February 8th-February 12th the following work is scheduled (pending weather issues):
Monday – Complete the tie-in at 870 Main St.
Tuesday – Fire Service tie-in at 824 Main St.
Wednesday – Tie-in at Falmouth Heights Intersection
Thursday –Domestic services for 850 Main St. and 5 Davis Straits
Friday – Clean up and paving
Please anticipate lane closures in the general area.