The plan for construction next week is as follows:
Monday 2/15 – Tie-in at Falmouth Heights Road
Tuesday 2/16 – Domestic Service for 5 Davis Straits and paving
After Tuesday the underground work will be complete, and they plan to return in mid to late March to complete the concrete restoration and punch list items.
Please note they are working on Monday, 02.15.2021: Presidents Day