DPW Engineering

Posted on: October 3, 2024

[ARCHIVED] Eversource duct bank work - ****3/14 UPDATE - Shining Sea Bikeway and Surf Drive Work****

marthas-vineyard-91-projects-falmouth

Eversource is working on a new submarine line between Falmouth and Martha's Vineyard that requires installation of duct banks in Falmouth roads and the Shining Sea Bikeway between Stephens Lane and Mill Road/Surf Drive.

Monday, March 17 - Friday, March 21 Update


SHINING SEA BIKEWAY:

Next Week:

  • Crews will continue pulling underground electric cable through the previously installed conduit or duct bank. 

 Please Note:

  • Work will continue through the winter months and is anticipated to be completed by early spring of 2025. A suggested detour is in place to accommodate work on the bike path, which is closed between Ter Heun Drive and Locust Street (see map below).
  • The Depot Ave parking lot, located at 81 Depot Ave, is also closed for the duration of this work. 

SURF DRIVE:

Next Week:

    • Crews will continue Horizontal Directional Drilling (HDD) work in the Mill Rd parking lot (located at Mill Road and Surf Drive). 
    • Crews will continue site prep and may begin HDD in the Surf Drive parking lot (located at Surf Drive and Shore Street). 
    • HDD is a construction technique that involves drilling a tunnel under a waterway or other designated area and pulling a pipeline through the drilled underground tunnel. At times, this work will be performed continuously, seven days a week (24/7).

Please Note:

  • A portion of the Surf Drive parking lot, located at 56 Surf Drive will be cordoned off and closed for the duration of this work.
  • The Mill Road parking lot, located at the corner of Mill Road and Surf Drive, is also closed for the duration of this work. 

Construction Hours: Monday through Friday, 7am-6pm


bike-detour

Occasional work may extend beyond the approved hours due to unforeseen circumstances, based on approval from municipal staff. For real time construction updates, please view online interactive construction map.

At this time, the construction will not interrupt your electrical service, and all people working on this project are Eversource-approved contractors and carry proper identification. If you have any questions or concerns regarding the project, please call 1-833-836-0302 or email at ProjectInfoMA@eversource.com.

Eversource is committed to deliver reliable energy to our customers and will begin constructing in early December, pending town approval, on a new 23-kV underground and submarine line between Falmouth and Martha’s Vineyard. Eversource is committed to open lines of communication and notifying the public about the project and pending construction. If you would like to learn more about the Project, please contact them. 

Website: www.eversource.com/MV-Reliability-91-Cable-Projects               

qr



Facebook Twitter Email

Other News in DPW Engineering

leaves falling

Fall Stormwater Leaf Removal Message

Posted on: October 14, 2025
marthas-vineyard-91-projects-falmouth

Eversource duct bank work - ****2/17 UPDATE ****

Posted on: September 15, 2025 | Last Modified on: February 17, 2026