Detailed update on timeline of work beginning next week for the water main replacement
During the week of April 1 to April 5 we will be mobilizing to start work. The project will begin on Oxbow Road possibly on April 4th. The first item of work is to replace four house services on Oxbow Road to install a new fire hydrant on Oxbow Road. On April 8th we expect to install a 20 inch line stop on the existing pipe at the intersection of Brick Kiln Road and Oxbow Road. Brick Kiln Road will be closed to eastbound traffic after Homestead. Expect traffic delays.