News Flash Home
The original item was published from 5/24/2019 11:37:58 AM to 6/1/2019 12:00:06 AM.

News Flash

DPW Water

Posted on: May 24, 2019

[ARCHIVED] Route 28/Main Street Water Main Replacement Update 5/24/2019

Latest plans for construction on the Route 28/Main Street Water Main Replacement

We are not doing any construction today, the Friday before Memorial Day weekend.

We will resume construction at 7:00 AM on Tuesday morning the 28th and will install the 16 inch diameter pipe on the south side of Teaticket Highway Tuesday, Wednesday and Thursday.

We will continue to reduce traffic to one lane around the construction zone.

We will be approaching Maravista Ave extension as we end the week. We expect to cross through that intersection early in the first week of June.

We have received permission from the Mass DOT to continue installing water main up through Friday the 14th of June.

We are on schedule to reach the intersection with Sandwich Road and intend to tie the new main to the existing main at Sandwich Road.

On Friday next week we will be installing hydrants at several locations on the new main.

There will be delays, seek alternative routes when necessary. Go to http://www.falmouthmass.us/986/Traffic-Updates to see the latest traffic plan


Additional Info...
Facebook Twitter Email