Weather continues to cooperate. We will be paving tomorrow, Friday the 10th.
We are getting 600 ft or more installed each week.
Next week we proceed from the vicinity of Library Lane towards Gifford Street.
There are no services on the north side as we go by the parks – Peg Noonan and the Library.
This will allow us to get a little more pipe than usual installed each day.
We will close the block that we are working on with the detour to Katherine Lee Bates.
Primary detour next week will be Library Lane to Shore Street.