DPW Water

Posted on: November 16, 2020

[ARCHIVED] Route 28/Main Street Water Main Replacement Update 11/16/2020

Work will resume on the Route 28 water main project with the installation of services between Jones Road and Falmouth Heights beginning on Wednesday, 11/18.  They will work the remainder of that week and then Monday and Tuesday the following week which is Thanksgiving week.  There will not be any work on Wednesday – Friday the week of Thanksgiving in the State Highway Layout, and the Contractor will return again starting on Monday 11/30 working in this stretch of Route 28 between Jones Road and Falmouth Heights. No major detours are scheduled just alternating lane traffic as necessary.