Next week is a short work week. We will be working 7 to 5 on Monday and Tuesday and 7- noon on Wednesday.
One crew will be finishing up the permanent trench paving on Teaticket Highway doing the stretch from the Homestead light to Falmouth Lumber.
Westbound traffic will be detoured to Brick Kiln Road, eastbound lane will remain open.
Second crew will continue with installing water main at the other end of the project on Palmer Ave next to the green.
The section of Palmer Ave next to the green will be closed to thru traffic