DPW Highway

Posted on: December 13, 2019

[ARCHIVED] Route 28/Main Street Water Main Replacement Update 12/13/2019

Crew No. 1 will be on installing pipe on Davis Straits from the Optometrist towards Dillingham Ave, and possible past Dillingham Ave if the weather cooperates.

Traffic will be alternating one way.


Crew No. 2 will be working at the Village Green installing pipe west towards Locust Street.

Traffic will be detoured on to Palmer Ave.


We will not be working December 23rd to December 27, so let me wish you all a great holiday.

Thanks to everyone for the cooperation and understanding.


We resume on December 30th and will be proceeding eastward on Main Street from the Village Green towards the Library.


Work hours are still 7 AM to 5 PM although we have been wrapping up a little early because it gets dark.

Additional Info...
Facebook Twitter Email

Other News in DPW Highway

Railroad Ave and Bike Path Closure 2/24/26

Posted on: February 20, 2026 | Last Modified on: February 20, 2026
marthas-vineyard-91-projects-falmouth

Eversource duct bank work - ****2/17 UPDATE ****

Posted on: September 15, 2025 | Last Modified on: February 17, 2026