Posted on: December 30, 2019

[ARCHIVED] Route 28/Main Street Water Main Replacement Update 12/30/2019

Water main construction will be proceeding down Main Street beginning Tuesday, December 31st. Beginning in front of the entrance to St. Barnabas Church we will be installing a 16" water main going eastward. 

There will be one lane alternating traffic up to Post Office Road. After that traffic will be detoured to Kathy Lee Bates Rd on a block by block basis. Each block will be posted as a no parking zone to allow construction to move as quickly as possible. 

We expect to install a least 150 feet each day will need 3-4 days for each block of work.

Pavement is only available one day each week, typically this will be Friday.

We will backfill and compact the trench each night but travel will be a little rough

Additional Info...
Facebook Twitter Email

Other News in DPW Highway

Railroad Ave and Bike Path Closure 2/24/26

Posted on: February 20, 2026 | Last Modified on: February 20, 2026
marthas-vineyard-91-projects-falmouth

Eversource duct bank work - ****2/17 UPDATE ****

Posted on: September 15, 2025 | Last Modified on: February 17, 2026