Posted on: May 17, 2019

[ARCHIVED] Route 28/Main Street Water Main Replacement Update 5/17/2019

We will continue to install the 16 inch water main in Teaticket Highway Monday through Thursday next week.

We will not work on Friday the 24th to minimize any traffic impacts as we roll into the Memorial Day Weekend.

As of Friday the 17th we have switched the alignment of the pipeline from the North Side of Route 28 to the South Side of Route 28.

We have a request in with Mass DOT to allow us to continue to construct after Memorial Day weekend up to Friday June 14th.

We anticipated a favorable decision on that request.

Traffic delays and lane closures are anticipated. Please seek alternative routes when possible. 

Additional Info...
Facebook Twitter Email

Other News in DPW Highway

Railroad Ave and Bike Path Closure 2/24/26

Posted on: February 20, 2026 | Last Modified on: February 20, 2026
marthas-vineyard-91-projects-falmouth

Eversource duct bank work - ****2/17 UPDATE ****

Posted on: September 15, 2025 | Last Modified on: February 17, 2026