[ARCHIVED] Route 28/Main Street Water Main Replacement Update 10/25/2019

We will have two work areas along Teaticket Highway next week.

Starting on Monday we will resume the installation of the 16 inch pipe.

We will start where we stopped last spring at the Teaticket Common.

We will zipper 150 to 200 feet of road each morning and will pave the trench at the end of each day.

Work hours are still 7 to 5 PM.


Traffic will be reduced to one lane around the work area.

Depending upon the available work area we may impose a detour for traffic travelling from west to east.

Additional Info...
Facebook Twitter Email

Other News in DPW Highway

Railroad Ave and Bike Path Closure 2/24/26

Posted on: February 20, 2026 | Last Modified on: February 20, 2026
marthas-vineyard-91-projects-falmouth

Eversource duct bank work - ****2/17 UPDATE ****

Posted on: September 15, 2025 | Last Modified on: February 17, 2026