[ARCHIVED] Route 28/Main Street Water Main Replacement Update 1/07/2020

We will continue to install the 16 inch main on Main Street next week.

As of the end of today we are east of Post Office Lane and will continue eastward next week.

Main Street during the day will be closed to through traffic from Post Office Lane to Library Lane.

Electronic signage will be updated daily to indicate what portions are open to local traffic.

On Monday we will start off with access to Town Hall from the Library Lane end with traffic routed down Walker to Chancery.

We will be by Town Hall Square end of day Monday and access on Tuesday will be from Post Office Lane end.

Wednesday and Thursday we work towards Library Lane and perhaps further.

Friday is for paving and we will need the entire area closed off. We will evaluate the ability to maintain one lane traffic.

Additional Info...
Facebook Twitter Email

Other News in DPW Highway

Railroad Ave and Bike Path Closure 2/24/26

Posted on: February 20, 2026 | Last Modified on: February 20, 2026
marthas-vineyard-91-projects-falmouth

Eversource duct bank work - ****2/17 UPDATE ****

Posted on: September 15, 2025 | Last Modified on: February 17, 2026